DFW Datacenter

Datacenters + VRF: A Natural Fit

✅ Short lead times on VRF equipment match the schedule demands of datacenter construction
✅ High VRF efficiency reduces the electrical load required for HVAC

# of Weeks, Not # of Months

Conventional HVAC equipment have lead times that extend beyond 6 months (some stretching to 18 months). Regardless of manufacturer (Mitsubishi, LG, Daikin), VRF equipment consistently ships on a 4-6 week schedule, helping datacenter projects hit their development timelines.

A More Profitable Use of Electricity

Electrical consumption is a top concern for datacenters. High-efficiency VRF systems cut the electrical demand tied to HVAC, freeing up capacity for higher-value uses, like the compute load the facility actually exists to serve.

212 Tons – Daikin VRF systems: (8) Heat Recovery Systems
(15)  3 Ton – Ductless mini split systems